Job Description |
Day (4/24-4/28) |
Estimated Start
Times |
Actual Start
Times |
Actual Completion
Times |
| Final
pre-5A SADMPROD load |
SADMPROD will be loaded as usual
after the close of business, Thursday, June 5th. Data will remain available as of the 5th
through 1st functional sign-off. |
6/6 |
9:00 PM |
9:10 PM |
5:57 AM |
| Migrate
5A from TEST to PROD |
5A version of the ETL catalog
and associated DMTools infrastructure will be migrated from SADMTEST to
SADMPROD |
6/6 |
8:00 AM |
5:00 AM |
5:30 AM |
| Execute
1st run 5A catalog in PROD |
Takes upwards of 10 hours per
iteration. Will attempt to have 1st
run complete prior to Friday night replication. |
6/6 |
8:00 AM |
5:59 AM |
1:21 PM |
| Validate
results from 1st run & User Signoff | Potential
Restore Point |
6/6 |
7:00 PM |
1:30
PM |
3:30 PM |
| Friday
night REPDB01 |
Replication may be delayed till
8:30. If the load is not complete,
assess time to completion. Replication
may be delayed till no later than 10:30.
If first load not complete, kill job & resubmit after REPDB01 is
loaded, adjust plan as needed. |
6/6 |
8:00 PM |
- |
- |
| Execute 2nd run 5A catalog in PROD |
Data as of Friday, 6/6 |
6/6 |
9:00 PM |
8:50 PM |
5:26 AM |
| Validate results from 2nd
run | Potential Restore Point -
Validate security, counts, content. |
6/7 |
8:00 AM |
5:56 AM |
8:30 AM |
| Migrate 5A Brio Data Models to PROD |
|
6/7 |
12:00 PM |
5:18 PM (Fri) |
8:11 PM (Fri) |
| Contact FDG |
Deb Fyler will send a notice to
the SDM Functional Developer Group notifying them of the availability and
status of 5A MODELS for/tables in SADMPROD |
6/8 |
8:00 AM |
|
|
| Begin Migration of 5A Brio Reports to PROD |
Actual due dates for 5A reports
begin 6/30… reports will roll into PROD as soon as they are completed |
6/9 |
|
|
|
| |
CUTOVER TO 5A
SDM COMPLETE |
6/9 |
|
|
|