Deliverables and Milestones for Implementation Phase starting 6/1/2006

Original Due Date

Revised Due Date

Completed Date

% Complete

Project Kickoff

6/2006

6/13/2006

6/13/2006

100

Academic Structure Finalized and Built

8/31/2006

9/7/2006

9/7/2006

100

Admissions Prototype (Recruitment)

9/2006

8/01/2006

100

Financial Aid Early Decision Prototype

12/2006

3/2007

3/30/2007

100

Student Records Prototype

3/2007

1/31/2008

100

Student Financials Prototype

3/2007

3/30/2007

100

Admissions Prototype (Applicant)

5/2007

7/6/2007

8/6/2007

100

Financial Aid Package and Award Prototype

8/2007

10/2007

10/31/2007

100

Financial Aid Disbursement Prototype

1/2008

5/2008

100

Implementation #1 –Focus on Admissions Recruitment

11/2006

11/13/2006

100

Implementation #2 – Focus on Admissions Applicant

8/2007

9/2007

9/6/2007

100

Implementation #3 – Focus on Financial Aid Profile Load

11/2007

10/26/2007

100

Implementation #4 – Focus on Student Records Pre Enrollment and Student Financials

3/2008

3/24/2008

100

Implementation #5 – Focus on Fin Aid Loan Processing

6/2008

6/2/2008

100

Implementation #6 – focus on Fin Aid NYS TAP, Student Financials Tax Reporting

9/2008

34

All systems fully on PeopleSoft

12/2008

Project Deliverables and Milestones for Detailed Planning Phase starting 12/1/2005

Original Due Date

Revised Due Date

Completed Date

% Complete

Project Phase Kickoff

12/9/2005

12/15/2005

12/15/2005

100

Functionality Reviews with Consultants

12/21/2005

1/20/2006

1/25/2006

100

Project plan (Revised)

1/13/2006

1/31/2006

100

Academic Structure Reviewed

1/13/2006

1/10/2006

100

Change Management Plan Complete

1/31/2006

1/31/2006

100

Financial Aid Fit Gap Complete*

2/24/2006

4/15/2006

4/15/2006

100

Recruitment IDP Complete*

2/28/2006

4/30/2006

5/5/2006

100

Records IDP 20% Complete*

3/20/2006

Milestone deleted

N/A

Student Financials Design Complete***

3/27/2006

5/31/2006

5/31/2006

100

Conversion Plan Complete - known at this time

3/25/2006

5/30/2006

5/30/2006

100

Interface Analysis Complete - known at this time

3/25/2006

5/31/2006

5/31/2006

100

Conversion Analysis Complete - SR and AD Prospect

3/29/2006

5/31/2006

5/31/2006

100

Training Plan Complete

3/30/2006

5/30/2006

4/06/2006

100

Test Plan Complete

3/30/2006

5/30/2006

5/30/2006

100

Security Plan Complete

3/30/2006

5/30/2006

5/30/2006

100

Technical Documentation Plan Complete

3/30/2006

5/30/2006

4/06/2006

100

Baseline Schedule (IDP Design/Prototype Phase)**

3/30/2006

5/30/2006

5/31/2006

100

Approve Implementation Schedule/Budget (Board of Trustees)**

4/15/2006

5/26/2006

5/26/2006

100

Hold Kick Off for Executing the Project**

4/30/2006

6/13/2006

6/13/2006

100

*Based on actual plan developed 1/31/06
**Extended approval based on Board of Trustees meeting 5/26
***IDP sessions completed on time - new definition of prototype task includes additional tasks

Project Deliverables and Milestones for High Level Planning Phase – completed 11/30/2005

Original Due Date

Revised Due Date

Completed Date

% Complete

Project Initiation

Develop Project Charter

7/28/2005

7/28/2005

100

Evaluate Project Charter

8/8/2005

8/8/2005

100

Approve Project Charter

8/30/2005

8/30/2005

100

Project Planning (High Level)

Prepare for the Project

8/30/2005

8/30/2005

100

Development of Recruiting Modifications and Conversions

8/30/2005

9/30/2005

9/30/2005

100

Review Historical Information and Business Cycle

9/1/2005

9/1/2005

100

Identify Project Team (Planning Team)

9/2/2005

9/2/2005

100

Project Website Go Live

9/15/2005

9/8/2005

100

Conduct Project Planning Kick – Off Meeting

9/16/2005

9/12/2005

100

Update Project Governance Model

9/30/2005

10/30/2005

100

Decide on Project Approach (Phases)

9/30/2005

9/30/2005

100

Complete Course Maintenance Plan

10/1/2005

10/1/2005

100

Develop the Project Initiation Plan

10/15/2005

10/27/2005

100

Submit the Project Initiation Plan to Project Directors for Approval

10/30/2005

10/28/2005

100

Present Project Initiation Plan to CF&PC

11/18/2005

11/14/2005

100

Confirm Approval to Proceed- Approved Project Initiation Plan

11/30/2005

11/14/2005

100